Jaringan Network dan Critical Path pada Website Sunia Decorations

Jaringan Network dan Critical Path disusun oleh:

Kelompok 4

Afilla Putri Sunia (10118268)
Adelia Oktaviani (10118126)
Fathan Fauzi (17118679)
Hamidah Nafa Lathifah (13118021)
Raka Dimaswara (15118862)
Reza Ridho Anshari (16118063)

WBS ( Work  Breakdown Structure) 

Task Mode

Task Name

Duration

Start

Finish

Predecessors

Manually Scheduled

1. Analisa dan Desain Sistem

1 day?

Thu 14/10/21

Thu 14/10/21

Manually Scheduled

   1.1 Menganalisa Kebutuhan sistem dengan melakukan wawancara terhadap Client

9 days

Fri 15/10/21

Wed 27/10/21

Manually Scheduled

   1.2 Membuat Data Flow Diagram (DFD)

1 day

Thu 28/10/21

Thu 28/10/21

2

Manually Scheduled

   1.3 Membuat Entity Relationship Diagram (ERD)

2 days

Fri 29/10/21

Mon 01/11/21

3

Manually Scheduled

   1.4 Dokumentasi Analisa & Desain Sistem

2 days

Tue 02/11/21

Wed 03/11/21

4

Manually Scheduled

2. Desain Aplikasi

1 day?

Wed 03/11/21

Wed 03/11/21

4

Manually Scheduled

   2.1 Membuat Desain Input

5 days

Thu 04/11/21

Wed 10/11/21

5

Manually Scheduled

   2.2 Membuat desain report

4 days

Thu 04/11/21

Tue 09/11/21

5

Manually Scheduled

   2.3 Membuat dokumentasi desain aplikasi

1 day?

Thu 04/11/21

Thu 04/11/21

5

Manually Scheduled

3. Pembuatan Program

14 days

Thu 18/11/21

Tue 07/12/21

6

Manually Scheduled

   3.1 Programing (Frontend dan Backend)

12 days

Fri 05/11/21

Mon 22/11/21

9

Manually Scheduled

   3.2 Dokumentasi Program

2 days

Fri 05/11/21

Mon 08/11/21

9

Manually Scheduled

4. Quality Assurance

3 days

Thu 09/12/21

Mon 13/12/21

10

Manually Scheduled

   4.1 Memastikan kualitas program

2 days

Tue 09/11/21

Wed 10/11/21

12

Manually Scheduled

   4.2 Dokumentasi Program

1 day

Thu 11/11/21

Thu 11/11/21

7

Manually Scheduled

5. Hosting Program

2 days

Tue 14/12/21

Wed 15/12/21

13

Manually Scheduled

   5.1 Instalasi program ke Internet

2 days

Thu 11/11/21

Fri 12/11/21

7

Manually Scheduled

6. Testing Program

3 days?

Fri 17/12/21

Tue 21/12/21

16

Manually Scheduled

   6.1 Melakukan uji pada program

1 day?

Mon 15/11/21

Mon 15/11/21

17

Manually Scheduled

   6.2 Dokumen Program

2 days

Mon 15/11/21

Tue 16/11/21

17

Manually Scheduled

7. Maintenance

3 days

Wed 17/11/21

Fri 19/11/21

20


Gantt Chart :


Network Diagram:


Tabel Aktivitas :

Kode

Aktivitas

Successor

Durasi

A

Analisa dan Desain Sistem

-

14

B

Desain Aplikasi

A

10

C

Pembuatan Program

A

14

D

Quality Assurance

A

3

E

Hosting Program

C,D

2

F

Testing Program

E

3

G

Copy Writer

B

2

H

Maintenance

G,F

3


Jaringan Network :


Critical Path :


Jalur Kritis = A, C, E, F dan H

Waktu Penyelesaian = 14 + 14 + 2 + 3 +3


Perhitungan ET :

Event j

Predecessor i

ETi + L

ETj

1

-

-

0

2

1

0 + 14 = 14

14

3

2

14+ 10 = 24

24

4

2

14 + 14 = 28

28

5

2

14 + 3 = 17

17

 

4

28 + 2= 30

30

6

5

30 + 3 = 33

33

7

3

24 + 3 = 27

27

 

6

33 + 3 = 36

36


Perhitungan LT :

nt j

Successor i

LTi - L

LTj

7

-

-

36

6

7

36 - 3 = 33

33

5

6

33 – 3 = 30

30

4

5

30 -2 = 28

28

3

7

36 – 3 = 33

33

2

3

24 – 10 = 14

14

 

4

28 – 14 = 14

14

 

5

30 – 3 = 27

27

1

2

14 – 14 = 0

0


Slack Event :

Event j

ETj

LTj 

 Slack Event j

1

0

0

0

2

14

14

0

3

24

33

9

4

28

28

0

5

30

30

0

6

33

33

0

7

36

36

0